How long does a house extension or renovation take, start to finish?

7 sections0%
Read time

3 min

Sections

7

Reviewed

September 2026. Costs are indicative 2026 UK ranges, not a quotation.

Key figures in this guide

People ask how long the building work takes. The build is u… Bathroom refit · 2-3 weeks · 2-3 weeks · 1-2 months Kitchen replacement · 3-6 weeks · 3-5 weeks · 2-3 mo… Single-storey rear extension · 10-16 weeks · 12-20 wee… Loft conversion, dormer · 8-14 weeks · 7-12 weeks ·…

One-minute decision

What are you trying to work out?

Recommended next step

Use the calculator with your own quantities and rates, then keep a contingency visible from day one.

Open calculator

People ask how long the building work takes. The build is usually the shorter half. From first idea to finished room, most extension projects in the UK run 9-18 months, and the paperwork is what stretches them.

Typical 2026 programme by project type

ProjectDesign and approvalsOn siteTotal
Bathroom refit2-3 weeks2-3 weeks1-2 months
Kitchen replacement3-6 weeks3-5 weeks2-3 months
Single-storey rear extension10-16 weeks12-20 weeks6-9 months
Loft conversion, dormer8-14 weeks7-12 weeks4-7 months
Two-storey extension12-20 weeks18-28 weeks8-12 months
Whole-house renovation16-26 weeks26-52 weeks12-18 months

These are 2026 UK norms for a well-run project with decisions made on time. The two most common causes of delay are late decisions on finishes and starting on site before the drawings are complete.

A realistic timeline for a single-storey rear extension

  • Brief and appointing a designer: 2-4 weeks.
  • Measured survey and concept design: 3-6 weeks.
  • Planning application or Lawful Development Certificate: 8-12 weeks from submission, plus 2-3 weeks to prepare it.
  • Technical design and structural engineering: 4-8 weeks, can partly overlap with planning at risk.
  • Building regulations approval: 5-8 weeks, or via building notice on simpler jobs.
  • Party wall notices and Award: 8-12 weeks, run in parallel from planning submission.
  • Tendering and appointing a contractor: 4-8 weeks.
  • Contractor lead-in before starting on site: 4-12 weeks for a good builder — the good ones are booked.
  • Construction: 12-20 weeks for a typical single-storey rear extension.
  • Snagging and completion: 2-4 weeks.

Loft conversions typically run 8-12 weeks on site. Two-storey extensions 16-26 weeks. A whole-house renovation, 6-12 months on site.

What the build weeks actually look like

Set-up and demolition, foundations and drainage, brick and blockwork to damp course, superstructure and steels, roof structure and covering, windows and doors, first fix services, plastering, second fix, decoration, external works. Foundations and roof watertight are the two milestones that matter most — after watertight, weather stops driving the programme.

What causes delay

  • Late decisions. A kitchen layout undecided at first fix stops electrics.
  • Variations. Every change re-prices and re-sequences.
  • Ground conditions. Deeper foundations near trees or old drains add weeks.
  • Long-lead items. Structural steel, bespoke glazing, sliding doors and specialist bricks can run 8-16 weeks. Order at technical design stage, not when the opening is ready.
  • Statutory sign-off. Building control inspections must happen before work is covered up.
  • Weather and holidays. Christmas typically removes two weeks; a wet January slows groundworks.

How to shorten it honestly

  • Overlap what can legitimately overlap: party wall notices during planning, structural design during determination.
  • Fix the specification before you tender. Decisions made once, early, are free.
  • Order long-lead items as soon as the design is technically fixed.
  • Appoint a contractor with a real start date, in writing, and accept that a builder available next week is often available for a reason.
  • Keep a contingency of 15-20% on the programme, not just the budget.

Living through it

Decide early whether you are staying. Staying saves rent but slows the build — protection, restricted hours and daily reinstatement all cost time. Moving out for the noisy phase alone is a common compromise.

Next step

Renovome Workspace generates a programme for your specific project from your answers about planning route, property type and complexity, then shows it as a schedule and Gantt chart, with dependencies so you can see exactly what a two-week delay to planning does to your finish date.

Last reviewed: September 2026. Costs are indicative 2026 UK ranges, not a quotation.

Community posts reflect individual experiences and opinions. They are not a substitute for advice from an appropriately qualified professional.

Apply this to your own project

Renovome Workspace turns guidance like this into a plan: a realistic programme, decisions tracked in one place, and matched professionals near you.